Chapter 11: Measurement and Payment
Anchor: #BIHBIJICSection 1: Introduction
Anchor: #b110001Overview
This chapter provides an overview of the measurement and payment process.
Anchor: #i1035775Procedure
Measure quantities in accordance with the contract as specified in Article 9.1, “Measurement of Quantities,” and Article 9.2, “Plans Quantity Measurements.” Pay Contractors according to the amount of work performed. Maintain sufficient documentation to support all quantities of work performed and payments made to the Contractor. Ensure the documentation supports:
- Anchor: #GQYKAQKM
- Contractor satisfaction of contract requirements, Anchor: #EUGLRRRR
- prompt and fair payment to the Contractor, and Anchor: #XDTVQVNF
- current, orderly, and accurate records.
Ensure that the Contractor completes work as provided in the contract before making payment.