Anchor: #CFADFCFF

Section 3: Water Resources

Anchor: #b120012

Storm Water Discharges

Ensure compliance with the Construction General Permit (CGP) issued by the Texas Commission on Environmental Quality (TCEQ) under its Texas Pollutant Discharge Elimination System (TPDES) permitting program for construction activities.

The CGP authorizes the discharge of storm water associated with construction activities that disturb one acre or more of total land area, including areas that are part of a larger common plan of development. Apply the CGP requirements only during site construction. The requirements of the CGP are complete once the earth-disturbing activities are completed, the area is finally stabilized, and a Notice of Termination (NOT), if a Notice of Intent (NOI) was required, is submitted to TCEQ.

Both the Department and the contractor are considered Primary Operators under the TPDES TX150000 Construction General Permit Part III, Section B.

    Anchor: #KLAGDQES
  • The Department is the primary operator with operational control over plans and specifications and is responsible for the development of the Stormwater Pollution Prevention Plan (SWP3).
  • Anchor: #LLCYGHCM
  • The Contractor is the primary operator with day-to-day operational control and is responsible for compliance with the SWP3 and permit conditions.
Anchor: #b120013

TPDES Construction General Permit (CGP)

In order to obtain permit coverage under the CGP:

    Anchor: #QTNSORQT
  • Develop the SWP3 prior to construction for each project of one acre or more of disturbance.
  • Anchor: #WWXEGNMA
  • Both the Department and the Contractor must post a completed Construction Site Notice (CSN).
  • Anchor: #DPDASGOK
  • Submit a Notice of Intent (NOI) to TCEQ if disturbance is five acres or more. Both the Department and the Contractor, as Primary Operators, are required to submit an NOI to TCEQ, if applicable, at least 7 days prior to the commencement of construction activities.
      Anchor: #EXOYGLLT
    • Submit the Department's NOI to TCEQ using the State of Texas Environmental Electronic Reporting System ( STEERS) available on the TCEQ website. Provide a copy of the completed and signed NOI to the Contractor’s use in completing the Contractor's NOI application/permit. Ensure that the NOI is signed by an authorized Department representative and contains the certification shown on the TCEQ NOI form. Prior to any construction activities, post the CSN.
    • Anchor: #PTHXMAIP
    • The Contractor will then use the information within TxDOT's NOI, as well as the construction plans and specifications to complete their NOI application.
  • Anchor: #KNOBGAES
  • Implement the SWP3 prior to beginning construction activities.
  • Anchor: #SDMFERCP
  • Both the Department and the Contractor must provide a copy of the signed NOI (for large construction activities) or CSN (for small construction activities) to the operator of any municipal separate storm sewer system (MS4) receiving the discharge, at least two calendar days prior to commencing construction activities.
  • Anchor: #NMWXLRJK
  • Perform scheduled inspections, together with maintenance and improvement actions, consisting of best management practices (BMPs) to prevent the discharge of pollutants.
  • Anchor: #GNIDFQPR
  • Submit a NOT using the State of Texas Environmental Electronic Reporting System ( Steers), if required, after completion of all required activities and final stabilization. Ensure that the NOT is signed by an authorized Department representative.
Anchor: #i1030345

Delegation of Signature Authority

The table below lists the documents requiring certification and individuals to sign certification.

Anchor: #t120002Documents Required to be Certified by TCEQ’s CGP

Document

Authorized Individual or Position

(For Projects Managed)

Legal Basis

Notice of Intent (NOI)

District engineer or division director or his or her immediate staff (e.g., director of operations); or area engineer. No further delegation allowed.

30 TAC §305.44, “Signatories to Applications,” requires principal executive officer having responsibility of overall operations over a geographic unit.

Notice of Termination (NOT)

Notice of Change (NOC)

Low Rainfall Erosivity Waiver Application

Construction Site Notice (CSN)

Inspection report certifications

Above and delegated to assistant area engineer, maintenance supervisor, project architects or engineers, or project inspectors with overall responsibility for the project. Personnel performing the inspections must be trained in the CGP regulations.

30 TAC §305.128, “Signatories to Reports,” requires position having responsibility for the overall operation of the facility activity, or environmental matters.

All other reports and information requested by the TCEQ executive director.



Anchor: #i1030323

Storm Water Pollution Prevention Plan (SWP3)

Prepare a SWP3 for projects as required by the CGP. The intent of the SWP3 is to reduce pollutants in storm water discharges from the project site. Ensure the SWP3 includes and addresses the following to the detail specified in the CGP.

    Anchor: #OXLNLTMU
  • Detailed site or project description including areas that are the responsibility of the contractor either within the ROW or within 1 mile of the ROW.
  • Anchor: #MXAHWRBU
  • Description of best management practices that will be used to minimize pollution in runoff.
  • Anchor: #LVLRAPSI
  • Description of any structural control practices used to divert flows away from exposed soils or to lessen the off-site transport of eroded soils.
  • Anchor: #DQFJTTLO
  • Description of any measures that will be installed during the construction process to control pollutants in storm water discharges that will occur after construction operations have been completed.
  • Anchor: #FDGHOLHE
  • Description of other controls, e.g., off-site vehicle tracking of sediments, generation of dusts.
  • Anchor: #YQOAUQQH
  • Ensure compliance with any state and local plans.
  • Anchor: #BFALUINP
  • Maintain all erosion and sediment control measures and other protective measures identified in the SWP3 in effective operating condition.
  • Anchor: #SBUIPTKF
  • Inspect disturbed areas of the construction site that have not been finally stabilized, areas used for storage of materials that are exposed to precipitation, and structural controls for evidence of, or the potential for, pollutants entering the drainage system.
  • Anchor: #NTRMHPVS
  • Identify and ensure the implementation of appropriate pollution prevention measures for all eligible non-stormwater components of the discharge.

Refer to the CGP for additional requirements.

TxDOT must maintain an up to date SWP3 Binder at the Area Office, field office or digitally for review upon request. The SWP3 can be paper or digital format. If the site is inactive or does not have an on-site location to store the SWP3, store the SWP3 at the Area Office. Ensure the CSN accurately reflects the location where the SWP3 is stored. The SWP3 must be made readily available at the time of an on-site inspection by a federal or state regulatory agency or local municipal separate storm sewer operating receiving discharges from the site. If the SWP3 is off-site, TxDOT will make the SWP3 available within 24 hours. The SWP3 should not be kept in a vehicle or other non-central location.

Anchor: #b120016

Contractor Involvement

In certain situations, the contractor is responsible for SWP3 preparation and obtaining authorization under the CGP. CGP authorization obtained by the Department does not cover contractor designated facilities off the ROW. When operations at a contractor Project Specific Location (PSL) trigger CGP requirements, the contractor is responsible for obtaining any CGP authorization.

For any contractor PSLs within 1 mile of any project limit, obtain at a minimum the following information from the contractor and maintain the information with the contract SWP3:

Anchor: #b120017

Inspections

Use Department Form 2118 – Construction Stormwater Pollution Prevention Plan Field Inspection and Maintenance Report to record and document inspections. Conduct regular inspections of the construction site at least once every 14 calendar days and within 24 hours of the end of a storm event of 0.5 inches or greater, or once every 7 calendar days regardless of rainfall. Describe how effectively the installed BMPs are performing. Note identified BMP failures during the inspection and describe any maintenance required due to the failure. If new BMPs are needed as the construction site changes, describe the BMP and the location of installation. Document temporary and permanent stabilization practices to determine if requirements are being met. Assign escalation ladder priorities to identified deficiencies. Obtain required signatures.

Include the following project areas in the inspection.

    Anchor: #CVGXMRHN
  • Disturbed areas of the construction site that have not been finally stabilized
  • Anchor: #NHNIYLPE
  • Areas used for storage of materials that are exposed to precipitation
  • Anchor: #OUFDRWQM
  • Structural control for evidence of, or the potential for, pollutants entering the drainage system
  • Anchor: #PERTBJVY
  • Sediment and erosion control measures identified in the SWP3 to ensure correct operation
  • Anchor: #ORNEIHHB
  • Locations of site vehicle exit for evidence of off-site sediment tracking
  • Anchor: #OBUGOALE
  • Areas where fence is down and wild animals, from deer to turtles, may be accessing the road
  • Anchor: #BWEBMBOH
  • Areas where equipment, moved earth, and other activities may have blocked wild animal access to culverts and bridges that are used to move beneath the road

Conduct inspections at least once every month:

    Anchor: #UPIHFIWO
  • where sites have been finally or temporarily stabilized,
  • Anchor: #OLDBFANU
  • where runoff is unlikely due to winter conditions (e.g., site is covered with snow or ice, or frozen ground exists), or
  • Anchor: #MAQIGEVP
  • during seasonal arid periods in arid areas (average annual rainfall of 0–10 in.) and semi-arid areas (average annual rainfall of 10–20 in.).

Modify the SWP3 based on the results of the inspection as necessary to include additional or modified BMPs designed to correct problems identified. For example, show additional controls on the site map; revise description of controls.

Complete revisions to the SWP3 within 7 calendar days following inspection. If existing BMPs need to be modified or if additional BMPs are necessary, complete implementation before the next anticipated storm event or as soon as practicable. Indicate modifications and added BMPs on the SWP3.

Anchor: #b120020

Work in Waters of the United States, Section 404

Section 404 of the Clean Water Act regulates the discharge of dredged or fill material into waters of the U.S. to restore and maintain the chemical, physical, and biological integrity of these waters.

Waters of the U.S. may include but, not limited to streams, wetlands, some open water, and stock ponds. The following common construction activities typically require a permit from the U.S. Army Corps of Engineers (USACE):

In order to comply with Section 404:

    Anchor: #HKQYWIFI
  • TxDOT must obtain any required USACE permit for proposed work before work begins in TxDOT ROW. Contractors are responsible for obtaining any off-site permits, including PSLs.
  • Anchor: #HNJXDOIY
  • Review the commitments pertaining to the USACE permit in the environmental permits, issues, and commitments (EPICs) section in the PS&E.
  • Anchor: #FYXGJQWD
  • Ensure that the contractor is aware of any waters of the U.S. in the area where work will occur, and make sure these are delineated prior to construction.
  • Anchor: #IJRUTMGQ
  • Ensure that the contractor is familiar with the work and associated impacts that have been authorized by the Section 404 permit.
  • Anchor: #EVLYBISX
  • Ensure that the contractor adheres to all agreements, mitigation plans, and BMPs required by the permit.
  • Anchor: #XCUASMVP
  • Review and approve any changes in the contract that may alter the USACE permit prior to work being conducted. When contractor-initiated changes to the issued Section 404 permit are desired, it is the contractor's responsibility to obtain a new or revised Section 404 permit from the USACE at the cost of the contractor. In this situation, no claims for schedule delays are allowed.
  • Anchor: #QBBQSRYP
  • Understand that failure to comply with all permit conditions may result in contract work stoppages being issued by the USACE or TxDOT.

For more information on Section 404 permit requirements, refer to the Environmental Handbook for Water Resources, or contact ENV's Natural Resources Management Section.

Anchor: #b120026

Work in Navigable Waters of the U.S., Section 10

Section 10 of the Rivers and Harbors Act requires that a project have authorization from the USACE if the project involves structures or work in or over any navigable water, and/or any obstruction or alteration of these waters. Section 10 permits are primarily intended to preserve the course, location, condition, or capacity of navigable waters. Structures (such as piers, wharfs, breakwaters, bulkheads, jetties, weirs, transmission lines, etc.) and work (such as dredging or disposal of dredged material, excavation, filling, or other modifications) in navigable waters require Section 10 permits.

In order to comply with Section 10:

    Anchor: #DKPGGQPA
  • TxDOT must obtain any required Section 10 USACE permit for proposed work before work begins in TxDOT ROW. Contractors are responsible for obtaining any off-site permits, including PSLs.
  • Anchor: #KXHWPMGI
  • Review the commitments pertaining to the USACE permit in the EPICs section in the PS&E.
  • Anchor: #AMXMCAXN
  • Ensure that the contractor is familiar with the work and associated impacts that have been authorized in the Section 10 permit.
  • Anchor: #VCDVMAJJ
  • Ensure that the contractor adheres to all agreements, mitigation plans, and BMPs required by the permit.
  • Anchor: #PITBHIBY
  • Review and approve any changes in the contract that may alter the USACE permit prior to work being conducted. When contractor-initiated changes to the issued Section 10 permit are desired, it is the contractor's responsibility to obtain a new or revised Section 10 permit from the USACE at the cost of the contractor. In this situation, no claims for schedule delays are allowed.
  • Anchor: #NFUADNOB
  • Understand that failure to comply with all permit conditions may result in contract work stoppages being issued by the USACE or TxDOT.

For more information on Section 10 permit requirements, refer to the Environmental Handbook for Water Resources, or contact ENV's Natural Resources Management Section.

Anchor: #b120025

Work in Navigable Waterways, Section 9

The U.S. Coast Guard (USCG) regulates bridges and causeways over navigable waters under the General Bridge Act and Section 9 of the Rivers and Harbors Act. Any project that will construct a new bridge or causeway, or reconstruct, or modify an existing bridge or causeway across a Section 9 navigable water will require a USCG bridge permit, bridge permit exception request, and/or a bridge lighting authorization.

In order to comply with Section 9:

    Anchor: #CXFLBDWU
  • TxDOT must obtain any required Section 9 permits from the USCG for proposed work before work begins in TxDOT ROW.
  • Anchor: #ALHHOPUU
  • Review the commitments pertaining to the USCG permit in the EPICs section in the PS&E.
  • Anchor: #YQPGSOWO
  • Ensure that the contractor adheres to the stipulations of the authorization/permit and associated best management practices.
  • Anchor: #QKSMHLJL
  • Review and approve any changes in the contract that may alter the USCG permit prior to work being conducted. When contractor-initiated changes to the issued USCG permit are desired, it is the contractor's responsibility to obtain a new or revised USCG permit at the cost of the contractor. In this situation, no claims for schedule delays are allowed.

For more information on Section 9 permit requirements, refer to the Environmental Handbook for Water Resources, or contact ENV's Natural Resources Management Section.

Anchor: #b120019

Work Over the Edwards Aquifer

The TCEQ administers the Edwards Aquifer Protection Program (EAPP) to prevent pollution of the Edwards Aquifer to protect groundwater use and maintain Texas surface water quality standards. If work involves soil disturbing construction activities in areas identified as the Edwards Aquifer Recharge Zone, Edwards Aquifer Contributing Zone, and Edwards Aquifer Transition Zone in the following eight counties, EAPP compliance may apply: Medina, Bexar, Comal, Kinney, Uvalde, Hays, Travis, and Williamson.

In order to comply with the EAPP:

    Anchor: #TQFIECMC
  • TxDOT must obtain any required EAPP authorization via required submittals such as a Water Pollution Abatement Plan (WPAP) or Contributing Zone Plan (CZP) from the TCEQ before work begins.
  • Anchor: #UQELASPI
  • Review the commitments made in the WPAP, CZP or other EAPP permit in the EPICs section in the PS&E.
  • Anchor: #WLXDRJEL
  • Ensure that the contractor adheres to the stipulations of the EAPP authorization including associated BMPs and performance of the work in accordance with contract requirements.
  • Anchor: #IEAYLWAY
  • Ensure that the contractor has the necessary information to recognize subsurface voids in bedrock. This information is available from the DEQC. If a subsurface void is encountered, the contractor must notify the DQEC. The void must be protected until an evaluation is completed and the contractor is cleared to continue work near the void.
  • Anchor: #NJSUDQIS
  • When contractor-initiated changes in the construction methodology affect the previously compliant impacts to the Edwards Aquifer, including encountering subsurface voids, immediately notify the district environmental coordinator and EAPP engineer, who may then need to notify the TCEQ and/or assist in obtaining a revised EAPP permit or void closure authorization. Contractor initiated changes will be the responsibility of the contractor, such as “In this situation, no claims for schedule delays are allowed.”

For more information on EAPP permit requirements, refer to the Environmental Handbook for Water Resources, or contact ENV’s Natural Resources Management Section.

Anchor: #i1036175

Work in Coastal Counties

Work in coastal counties including Orange, Jefferson, Chambers, Harris, Galveston, Brazoria, Matagorda, Jackson, Calhoun, Victoria, Refugio, Aransas, San Patricio, Nueces, Kleberg, Kenedy, Willacy, and Cameron counties, may trigger Coastal Zone Management Act (CZMA) compliance requirements under the Texas Coastal Management Program (TCMP).

In order to comply with CZMA and the TCMP:

    Anchor: #LNFKNJDW
  • TxDOT self-certifies its transportation projects as consistent with the goals and policies of the TCMP by avoiding impacts. TxDOT must obtain any required documentation for consistency with the TCMP for proposed work before work begins in TxDOT ROW. Contractors are responsible for obtaining any off-site permits, including PSLs.
  • Anchor: #WRIPUNYK
  • Review any commitments pertaining to the TCMP and/or USACE permit in the EPICs section in the PS&E.
  • Anchor: #XRYUTAQM
  • Ensure that the contractor adheres to the stipulations of the authorization/permit and associated best management practices.
  • Anchor: #MNDSQOFP
  • Review and approve any changes in the contract that may alter the TCMP commitment and/or USACE permit prior to work being conducted. When contractor-initiated changes that alter the TCMP consistency or any USACE are desired, it is the contractor's responsibility to obtain a new or revised permit from the USACE at the cost of the contractor. In this situation, no claims for schedule delays are allowed.

For more information on CZMA and TCMP requirements, refer to the Environmental Handbook for Water Resources, or contact ENV’s Natural Resources Management Section.

Previous page  Next page   Title page